North City Reservoir: more than meets the eye

Tower View 002 med crop

3.7 MG gallong reservoir water tank shorelineIf you’ve been driving in the vicinity of 15th Avenue NE and NE 177th Street, you’ve no doubt noticed the work taking place on our 3.7 MG North City Reservoir. While it may appear to be nothing more than a repainting project, it’s ever so much more, as shown in the timeline below.

A water reservoir serves two purposes: to hold water in reserve, and to maintain proper water pressure within a given service area. When we added a second water source in 2013 (Cedar River, in addition to our Tolt Watershed connection), we were able to take a fresh look at how water pressure was maintained throughout our system.

IMG_2569 editedOur studies showed that adding a new Pump Station, along with internal upgrades to our 3.7 MG reservoir, would provide enhanced water pressure for the least possible cost—despite having to demolish the old 0.4 MG reservoir to make room for the new Pump Station. Because crews would already be on site for the 3.7 MG reservoir’s interior upgrades, it made sense to have it repainted at the same time.

However, repainting the reservoir was not a simple task, since it was home to a number of antennas owned by various wireless carriers in our area. In order to repaint the reservoir, all of these antennas had to be relocated—requiring months of discussions, negotiations, and agreements with each carrier.

As of this writing, we’ve negotiated new, long-term antenna leases with each carrier, a large crane is installing a railing on top of the reservoir, onto which the wireless carriers will install their antennas. The new Pump Station will be going out to bid in August, awarded in September, and construction is anticipated to begin shortly after.

So the next time you look up at the reservoir and admire its fresh coat of paint, remember it’s just one of many improvements we’ve made recently to make our water operations more efficient, and to handle a large amount of water without building a new reservoir.

If you have any questions about this project (or other projects), please call 206.362.8100.

Timeline of the North City Reservoir Project

2007

  • Begin lease discussions with wireless carriers re: 3.7 MG Reservoir Upgrade, new Pump Station and new Carrier Bldg.

2008

  • Begin Pump Station predesign study

2009

  • Begin design of 3.7 MG Reservoir Upgrade project (interior and exterior)

2010

  • Continue lease negotiations with wireless carriers
  • Begin discussions with the Health Department

2011

  • Plan, permit and demolish the 0.4 MG Reservoir
  • Begin site planning and lot line adjustment
  • Select new Pump Station designer

2012

  • Finalize and sign new wireless carrier leases
  • Obtain 1% financing for the Pump Station Project through Washington State’s Drinking Water State Revolving Fund
  • Begin designing the new Pump Station
  • Select designer and design the Carrier Building

2013

  • Sign remaining wireless carrier leases
  • Obtain permit and construct new Carrier Building
  • Finalize design and obtain permit for 3.7 MG Reservoir Upgrade project

2014

  • Complete 3.7 MG Reservoir Upgrade project
  • Obtain permit and begin constructing new Pump Station

2015

  • Complete Pump Station Project